June 2019: Opera House and Bruske Hall Construction Updates

June 14, 2019

The Opera House

The Opera House renovation is still on schedule for completion by mid-August. Recent progress includes installation of carpet on the third floor and in the student apartment bedrooms. All floor tile on the third floor is finished, with tile in all of the living spaces nearly complete. Cabinets have been installed in the living spaces, and countertops will be added by the end of the month. Finishes are being made on the third floor. The lobby area framing is nearly complete, with the flooring being installed next month.

cabinets

cabinets

cabinets

carpet

carpet

tile

framing

lobby

 Bruske Hall

Bruske Hall construction is in progress. Current work includes drywall on all floors, abatement through the second floor and demolition of the first floor. All bathrooms will be framed by next week. Floor tile on the ground and first floors will be started next, along with drywall on the second floor, fire suppression at the third floor, earthwork and utilities.

drywall

drywall

drywall

drywall

drywall

framing

 



Story published on June 13, 2019